Process Simulation for Lean Manufacturing

System Engineer

  • Objective: Address bottlenecks between Acid and Wire Drawing Processes and optimize system efficiency.

  • Analysis: Conducted simulation with Acid Processes operating on 3 shifts and Wire Drawing Processes on 2 shifts.

  • Findings: Identified low utilization of 12 Wire Drawing machines and a bottleneck between Acid and Wire Drawing Processes.

  • Solution: Implemented an optimized shift schedule for both processes to maximize production

  • Outcomes: Enhanced machine utilization, eliminated bottlenecks, reduced costs by 5%, and increased production by 8% while minimizing total input time for Wire Rods.

3D Bin Packing Optimization using Mathematical Modelling

Competitor

  • Objective: Maximize truck fill rates through efficient 3D bin packing.

  • Analysis: Conducted a literature review on existing 3D bin packing algorithms and developed a new algorithm by refining current methods to enhance fill rates.

  • Findings: Existing heuristic approach led to low fill rates due to inefficiencies in the bin packing process.

  • Solution: Designed and implemented a 3D bin packing optimization solution.

  • Outcome: Achieved 11% increase in truck fill rates, enhancing overall operational efficiency.

3 D BIN PACKING OPTIMIZATION USING MATHE

Traffic Flow Optimization

Developer

Coming soon...